Brookside Gardens Master Plan Implementation (P078702)

  • Category: M-NCPPC
  • Sub Category: Development
  • Administering Agency: M-NCPPC (AAGE13)
  • Planning Area: Kemp Mill-Four Corners
  • Date Last Modified: 3/6/14
  • Required Adequate Public Facility: No
  • Relocation: Impact None
  • Status: Final Design Stage

EXPENDITURE SCHEDULE ($000s) 

FUNDING SCHEDULE ($000s)

OPERATING BUDGET IMPACT ($000s)

Description

This project implements Phases I, II and V of the Brookside Gardens Master Plan, at 1800 Glenallan Avenue, Wheaton. The phased implementation in the CIP is as follows: Phase I: facility planning, design and construction of the Visitors Center entrance. Phase II: facility planning, design and construction of the expanded parking lot and stormwater management. Phase V: design and construction of a new greenhouse and plant propagation facility to consolidate growing areas and provide operational efficiencies and budget savings. Phase III deals with stream stabilization along the perimeter of Brookside Gardens and Phase IV includes improvements in Gude Gardens. Both phases are being coordinated through this PDF and other related funding sources.

Location

1800 Glenallan Avenue Wheaton, MD 20902

Estimated Schedule

Design for Phases I and II were combined and commenced in FY12, with construction completion expected in FY15. Phase V design and construction scheduled in FY15.

Cost Change

The addition of Phase I to this ongoing project increased the scope of this project. Also, Phases I and II have seen cost increases beyond the 2010 estimates due to market conditions and increased stormwater management (SWM) regulations that require SWM plans with increased areas of pervious surfaces and bioretention.

Justification 

Visitor Survey (1995). Brookside Gardens Master Plan (2004), including data from several focus groups held during the planning process and public testimony at planning board hearings. Renovations address critical maintenance needs for the 44 year old facility that has become one M NCPPC's most popular facilities. 1995 Visitor Survey. Brookside Gardens Master Plan approved by Montgomery County Planning Board, March 3, 2005. The Montgomery County Planning Board approved the following facility Plans: Phase I (entrance), July 17, 2008; Phase II (parking expansion and drop-off), February 25, 2010; and Phase V (greenhouse), June 13, 2013.

Fiscal Note

A private donation of $1 million has been offered to Brookside Gardens and the Montgomery Parks Foundation for construction of a new plant production greenhouse, provided the Parks Department can acquire the remaining funding for the greenhouse and supporting infrastructure. $1.2 million in Program Open Space funds will be allocated for construction of the new greenhouse.

Disclosures

A pedestrian impact analysis has been completed for this project. M-NCPPC (A13) asserts that this project conforms to the requirements of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.

Coordination

Friends of Brookside Gardens, Montgomery County Department of Environmental Protection, Public Arts Trust, Small Grants/Donor Assisted Capital Improvements, PDF 058755, Montgomery County Department of Transportation